Campus Construction Update

Frazer Hall

The mechanical improvement plans are under review. They are in the Design Development Stage. This project will incude the replacement of the current air handlers and a replacement chiller.



Bubble Removal

After the Pohl & Stark Buildings are completed, the temporary facility will be removed. Future plans for this site are still undetermined.



Fine Arts


Fine Arts' initial phase is complete (building weather proofing). MUW is in possession of the building as of August 23rd, 2005. Interior renovations are to begin as soon as FEMA and MEMA finalize interior plans. Plans are under review at this time.



Emma Ody Pohl Building and the Marie Charlotte Stark University Recreation Center

Click Here to View Live Image!

The Pohl/Stark building is now 99% compete. Construction is progressing nicely. Exterior work will continue. Finish materials are being installed in the interior. Completion is scheduled for mid February. The architect's inspection is scheduled for February 1st.

The exterior fencing is down around most of the perimeter. Please do not enter this construction site at any time for any reason. The temporary parking lot is still open for use. Please exit on 11th towards 7th Ave. S.













View Live Image!
 
Poindexter:

Design development plans are underway for Poindexter. Preliminary estimates show a construction time of 12-18 months. This project has not went out for bid. A start date will be some time in spring 2007.







Eckford:

 
This project began on August 1st. Construction is scheduled for completion by early spring. Interior finish work has begun. Most outside site work has been completed except for the final grading.

Please do not enter this construction site at any time for any reason.  The
temporary parking lot behind Martin is CLOSED.  Do not park between the
campus fence on 11th street and the construction fence.  Damage to your
vehicles may occur from vehicles entering the construction site.

Shackleford:

Construction began on November 1st. Delivery of the stairs will hopefully occur by the middle of February. This project has a completion date of July 31, 2007. MSMS is occupying the building during construction. Interior work will mostly be done during holidays.



Painter:

Shafer and Associates have begun the study of the building for the Mechanical renovations and elevator addition. Design work will continue over the next several months. Preliminary designs are underway. Submittals to Archives & History will begin shortly.



Storm Drainage and Street Repair:

The storm drainage project plans have been submitted to the Bureau of Buildings. An approval will allow this project to go out for bids. The first phase of the project will clean and video almost all of the storm drains on the south half of campus. Any remaining funds will be used for street repair.



Please be careful this next month as most of the projects still involve outdoor construction and site cleanup.

Photographs by Joshua Hollis.